September 2013
Dear Customer
Sewer improvement work – Church Road, Uppermill
Every time you take a shower, wash the dishes or flush the toilet we make sure your wastewater is taken away.
However on Church Road, the sewers are struggling to cope with the demand being put on them particularly during heavy periods of rainfall, resulting in sewer flooding to some properties.
We need to carry out a series of utility diversions to ensure we can start our major sewer work as planned.
How this may affect you
The work will start on the 16 September 2013 and will last around 13 weeks.
Work to take place will be
- Moving a clean water pipe
- Moving a BT cable
- Moving a gas main
- Moving Electricity cables
The work will involve moving the above utilities so that our new sewer can be installed as quickly as possible.
During the works there will be some temporary traffic lights, close to Pickhill Lane, where the works are being carried out. Vehicles will be able to travel down Church Road in both directions.
We are due to be starting our major sewer work on Church Road at the beginning of October but will write to you again closer to the time, we will also hold a public exhibition, where we can tell you about our project and what it will involve.
Still have a question? Call: 0845 746 2200 quoting project number NCA 80029009
We’ll be happy to help.
Yours faithfully
Customer Services
Slightly confused with this story. Is it starting September 16th or October?
The info I’ve been given indicates a full Church Road closure yet this story says there will be traffic lights.
I believe it’s 17th Oct 2013 to 31st March 2014